February 11, 2005
1. Made this project website
2. Met with Andrew Bata and Isaac Takyi of NYCT to discuss my project and their related work and insights
3. Updated the outline
4. Made contacts with Seattle
February 25, 2005
Since last writing up my work, week I:
1. Distributed the survey online.
2. Wrote up the GPS section.
3. Made contact with various MTA-analytical groups.
4. Read various Transportation Research Board publications.
5. Read several other sources.
March 6, 2005
1. Completed significant data entry for surveys (approx 170 submitted so far)
2. Wrote economic development section
3. Wrote section on schedules vs. arrival times
4. Filled out and revised outline
5. Determined goal of 50 pages